Memorandum of Understanding
Between

Chhattisgarh State Industrial Development Corporation Limited (CSIDC)
AND 

Sanvijay Rolling & Engineering Limited
Nagpur

For
Sponge Iron, Steel Making Plant, Coal Washery, Rolling Mill and Captive Power Plant
in
Chhattisgarh 

21st April 2003
at


Raipur 

MEMORANDUM OF UNDERSTANDING

            Between the Chhattisgarh State Industries Development Corporation (CSIDC) which is the industrial promotion agency of the Government of Chhattisgarh and M/s Sanvijay Rolling & Engineering Limited, Nagpur for setting up a new mega project of Sponge Iron, Steel Making Plant, Coal Washery, Rolling Mill and Captive Power Plant at Raigarh & other places with an investment of over Rs.400 Crores.

            This memorandum of understanding (MOU) is made on this 21st day of April   2003 at Raipur between CSIDC hereinafter referred to as the “Corporation” which expression shall, unless repugnant to the context of the meaning there of include its successors of the first part.

A N D

            M/s Sanvijay Rolling & Engineering Limited, a company incorporated under the Indian Companies Act 1956 (1 of 1956) and having its registered office at 9-Imambada Road, Nagpur 440018 (hereinafter referred to as “SREL” which expression shall unless repugnant to the context or the meaning thereof include its successors of the other part.

            And where as SREL is desiring of setting up a Sponge Iron Project, Steel making & Captive Power Plant, Coal Washery, Rolling Mill, Iron ore Mining & Coal Mining etc. at District Raigarh and other places with proposed investment of 465 crores in all phases.

          Plant / Facility                            Installed Capacity                         Project Cost

                                                             in Phases                                        (Rs. crores)

1.      Sponge Iron                                3,20,000                                                       120

2.      M.S.Ingots & Billets                  2,00,000                                                         65

3.      Rolling Mill                                1,00,000                                                         50

4.      Power Plant                                40 MW                                                         120

5.      Coal Washery                                                                                                    40

6.      Coal Mining

7.      Iron Ore Mining & other                                                                                  70

8.      Total                                                                                                                465

            Whereas, the “Corporation” acting on behalf of the Government of Chhattisgarh agrees to provide all help, prevailing incentives and facilitate clearances necessary for aforesaid projects in the State of Chhattisgarh including allotment of Land at Raigarh and Iron Ore & Coal Mining Blocks in Chhattisgarh consistent with the various constitutional and statutory provisions relating to the area of the said project on the “Corporations” initiative as well as through the intervention of the State Investment Promotion Board under the Chhattisgarh Investment Promotion Act-2002 (hereinafter referred to as the act).

            Now therefore Corporation & SREL have agreed to do and hereby execute the MOU in order to enable such a large private sector investment in the state of Chhattisgarh and for the aforesaid the parties hereto have agreed upon the terms assurances, obligations and commitments as set out herein below:

1.         It is agreed by the parties hereto that SREL will set up the aforesaid projects in the state of Chhattisgarh, where in the Corporation & the state government agencies & departments will extend fullest co-operation for successful implementation of these projects.

2.         The Corporation will facilitate allotment of optimum land, free from all encumbrances to SREL in Raigarh District and other places under prevailing rate as per policy applicable for mega projects.

3.         The Corporation will facilitate availability of 4 MGD of water for project as per assessment from viable sources. The Corporation shall also facilitate assistance in laying of water pipeline from source to the site and will assist in getting necessary clearances, approvals etc. particularly from Forest & Revenue Departments.

4.         The Corporation shall facilitate all incentives available to investors under this MOU as per policy of the state Govt. and appropriate authorities under the provision of State Investment Promotion Act 2002 for the project specifically, it is understood that such incentives will relates to:

A)        Waiver of electricity duty on consumption of electricity for a period of 15 years for Industries from the date of commencement of production by units which is already provided for in terms of the Industrial Policy of the State Government of Chhattisgarh.

B)        Exemption from Entry Tax in respect of Capital Goods & Raw Materials, incidental goods etc. for the proposed projects, as per Industrial Policy of the Chhattisgarh Government.

C)        Exemption from payment of Sales Tax as per the policy of Government of Chhattisgarh.

D)       Waiver of Stamp Duty & Registration Fee in connection with the 

implementation of the Projects will include Land, Bank Loan & Mortgage etc. as per Industrial Policy of State.

E)        Waiver of service charges in acquisition of land, as per policy of the Government for Mega Projects.

F)        The Corporation will facilitate disbursement of infrastructure support to the extent of 25% of the infrastructure cost, as per Industrial Policy.

G)        The Corporation will facilitate assistance with CSEB to provide  electricity to SREL under prevailing terms & conditions and as per Power Policy of the State Government.

5.         Consistent with the State Government’s policy on Captive Power Plants, Corporation shall assist in obtaining expeditiously all relevant approvals from CSEB and other competent authorities, so as to enable SREL to set up the Captive Power Plant and Wheel Surplus Power to sister associates concerns through CSEB grid after paying charges as prescribed by the Board and as per Captive Power Policy of Government of Chhattisgarh.

6.         Any new or special incentives which may be considered or announced by the Govt. of Chhattisgarh in future or after signing of this MOU, the same may be provided to SREL.

7.         The Corporation will facilitate grant of Coal & Iron Ore mining lease and also facilitate State Government’s recommendation to the Government of India for allotment of Coal & Iron Ore Blocks.

8.         SREL will initiate all necessary steps to implement the projects under the MOU with a view to contribute to the Industrial Development & Economic Growth of Chhattisgarh.

9.         The Industry shall earmark separate funds for environmental upgradation and social upliftment of surrounding areas/villages etc.

10.       The SREL will facilitate for setting up of ancillary/auxiliary industries by CSIDC or any Government agency.

11.       The SREL will provide employment to local people as per the Govt. policy.

12.       The SREL will make provision as per law for utilization and disposal of Fly Ash generated in their power projects.

 

            For witness where all the parties hereto have set their hand to this MOU on this 21st day of April 2003.

SIGNED AND DECLARED BY :

1.         For CSIDC

            (A Govt. of Chhattisgarh Undertaking)

            --sd--

            (Amitabh jain)                                      

            MANAGING DIRECTOR

2.         For Sanvijay Rolling & Engineering Limited, Nagpur

--sd--                                                               --sd--

            (Ramesh Kumar Pachisia)  (Sanjay P. Agrawal)

 

WITNESSES:                                                        WITNESSES:

1. ................................................                            1. ................................................

 

 